New World Development Company Limited
234
Principal Projects Summary
No.
Name of Projects
Capacity/
Installed Capacity
NWSH’s
Form of
Investment
NWSH’s
Attributable
Interest (%)
Expected/
Actual
Operation
Date
Year of
Expiry
(1)
Environment
E22
Chongqing Construction Company
Equity
20.3*
2038
Sludge Treatment
240 tonnes/day
2nd half of 2016
(Estimate)
E23
Chongqing CCIP Water Treatment Plants
Equity
25.3
2055
Waste Water
40,000 m
3
/day
3/2010
Industrial Water
120,000 m
3
/day
3/2010
E24
Chongqing Environmental R&D Centre
N/A
Equity
15.6
11/2013
2043
E25
Wuhan Chemical Industry Park Water Treatment Plants
Equity
21.5
2041
Waste Water
10,000 m
3
/day
12/2013
Industrial Water
50,000 m
3
/day
9/2013
E26
Tianjin Jieyuan Water Plant
500,000 m
3
/day
Equity
50.0
8/2002
2022
E27
Tanggu Water Plant
310,000 m
3
/day
Equity
24.5
4/2005
2034
E28
Xinchang Water Plant
100,000 m
3
/day
Equity
25.0
3/2002
2032
E29
Changshu Water Plant
Equity
24.5
2036
Phase I
675,000 m
3
/day
9/1984
Phase II
200,000 m
3
/day
11/2012
E30
Changshu Waste Water Plant
Equity
24.5
2036
Waste Water (O&M^)
100,000 m
3
/day
3/2015
E31
Jiangsu Water Company
Equity
25.0
2037
Water
350,000 m
3
/day
10/2007
#
Waste Water
300,000 m
3
/day
10/2007
#
E32
Suzhou Industrial Park Sludge Treatment Plant
Equity
24.5
2039
Phase I
300 tonnes/day
5/2011
Phase II
300 tonnes/day
7/2016
E33
Yangzhou Sludge Treatment Plant
300 tonnes/day
Equity
10.4
5/2016
2044
E34
Suzhou Xiangcheng Sludge Treatment Plant
200 tonnes/day
Equity
12.5
2nd half of 2017
(Estimate)
2046
E35
Sino French Solutions Company
Equity
50.0
10/2013
N/A
E36
Far East Landfill Technologies Limited
35 million m
3
Equity
47.0
6/1995
2045
E37
Shanghai SCIP Waste Incineration Plant
Equity
10.0
2053
Phase I
60,000 tonnes/year
8/2006
Phase II
60,000 tonnes/year
2nd half of 2016
(Estimate)
E38
Chongqing Derun Environment Co., Ltd.
N/A
Equity
12.6
10/2014
#
N/A
E39
Chongqing Silian Optoelectronics
Science & Technology Co., Ltd.
N/A
EJV
20.0
7/2008
N/A
E40
Zhujiang Power Station — Phase I
600 MW
EJV
50.0
1/1994
2017
E41
Zhujiang Power Station — Phase II
620 MW
EJV
25.0
4/1996
2020
E42
Chengdu Jintang Power Plant
1,200 MW
Equity
35.0
6/2007
2040
E43
Guangzhou Fuel Company
EJV
35.0
2033
Coal Pier
7 million
tonnes/year
1/2008
Water and industrial water treatment
7,001,000 m
3
/day
Demineralised water
4,800 m
3
/day
Waste water treatment
1,038,350 m
3
/day
Sludge treatment
1,340 tonnes/day
Waste management
120,000 tonnes/year
Landfill
35 million m
3
Power plants installed capacity
Coal pier handling capacity
2,420.0 MW
7 million
tonnes/year
^
O&M stands for operation and management consultancy services
#
Date of incorporation
*
To restructure the water projects in Chongqing, NWSH’s interest in Chongqing Construction Company was injected into Chongqing Tangjiatuo
Waste Water Plant in September 2016
Project Summary – Infrastructure Projects
(continued)